The Warranty Expired in the Laydown Yard: Equipment Warranty as a Supplier Data Problem

14 min read • 23 October 2026
The Warranty Expired in the Laydown Yard: Equipment Warranty as a Supplier Data Problem

Of all the things a capital project hands its operating organization at completion, the equipment warranty is the one everybody assumes is there. It is in the purchase order. It is a condition precedent to final completion in most EPC contracts. It was priced. The uncomfortable arithmetic is that on a multi-year build, the warranty on major equipment is frequently expired, or weeks from expiring, on the day the plant is first run – not because a supplier behaved badly, but because the standard market formula starts the clock at shipment.

This is not a legal curiosity. It is a supplier management failure with a quantifiable cost, and it is invisible to the project because nobody holds the three or four data fields that would make it visible.

The formula: twelve from start-up or eighteen from shipment, whichever ends first

Flowserve Corporation, Worldwide Terms and Conditions of Sale, Section 4: “If it appears within twelve (12) months from the initial Equipment startup or until eighteen (18) months after shipment, whichever occurs first, that the Equipment or any part thereof does not conform to this warranty … Seller shall thereupon promptly correct such nonconformity by repair or replacement EXW Seller’s factory or service center.”

The same structure appears, independently, across the market:

  • Siemens, Standard Terms and Conditions of Sale for Products, Article 9(d): notice must be given by “the earlier of twelve (12) months from initial operation of the Product or eighteen (18) months from shipment.”
  • TotalEnergies, Spot Contract for Supply of Goods and/or Services (OTGTS), Clause 3.13 – the buyer’s own standard: twelve months from first use or eighteen months from the delivery date, “whichever period ends first.”
  • World Bank, Standard Bidding Documents – Procurement of Goods, GCC 28.3: twelve months after acceptance at final destination “or for eighteen (18) months after the date of shipment from the port or place of loading in the country of origin, whichever period concludes earlier.” EBRD’s General Conditions for Supply of Goods carry the same formula.
  • ABB Electrification, General Terms and Conditions of Sale 01-2026, Art. 8(a): “twelve (12) months after installation or eighteen (18) months after date of shipment, whichever first occurs.”
  • Atlas Copco Compressors, Standard Terms and Conditions of Sale, Rev. March 2024, §7(a): fifteen months from shipment or twelve months from initial start-up, whichever occurs first – and, critically, “In the event Goods are put into storage due to Purchaser’s inability to take delivery, the above warranty starts on the day of delivery into storage.”
  • Sulzer, General Conditions for Supply, Rev 1, 11 March 2026, §6.2: the earlier of twelve months from initial operation or eighteen months from availability for delivery – a trigger that precedes delivery itself.

Some suppliers do not offer a start-up clock at all. Alfa Laval Inc.’s Canadian standard terms (1 August 2026) warrant for “one (1) year from the date of initial delivery.” KSB’s general conditions run “24 months from the date on which the Goods are made available.” Siemens Energy AG’s general delivery conditions for its product business give 24 months from unloading at the purchaser’s site, with an absolute backstop: “the warranty period shall end no later than 30 months from the date of notification.”

And for the item with the longest lead time in the entire plant, the clock is the worst. JCL Energy’s limited warranty for new liquid-filled and air-cooled transformers runs “eighteen (18) months from the date of shipment or one (1) year from the date of energization of the Transformer, whichever occurs first.”

Two further features compound the problem. Repaired or replaced parts are re-warranted only for the remainder of the original period (Flowserve, Siemens), so a warranty repair at month seventeen buys one month. And the remedy is typically ex works the factory, with the buyer bearing access, removal, reinstallation and transport.

Now do the arithmetic

Wood Mackenzie’s survey of grid equipment lead times, published with American Clean Power in September 2025, put power transformers at an average of 128 weeks in Q2 2025 and generator step-up transformers at 143 weeks, with high-voltage switchgear at 44 weeks. The IEA reported in February 2025 that procurement takes two to three years for cables and up to four years for large power transformers, with DC cables extending beyond five. GE Vernova told the market in April 2026 that heavy-duty gas turbine lead times run about three years, with roughly 10 GW of capacity remaining across 2029 and 2030 combined.

Then the schedule moves. McKinsey’s November 2024 study of 80 global mining projects found average real schedule delays of approximately 25%, rising to 52% for megaprojects. Bain’s analysis of upstream and midstream oil and gas capital projects from 2015 to 2019 found average delays of 2.5 years.

Put those together on a GSU transformer. It ships roughly 2.75 years after order. The eighteen-month shipment clock expires about sixteen months later. If the project then slips anywhere near the megaproject average, the transformer is energised with no warranty at all, and the one-year-from-energisation limb never starts because the other limb already ended it.

Two clocks, two start dates, and the owner owns the difference

The EPC contract does not close the gap; it runs on a different clock. FIDIC’s Silver Book (2nd edition, 2017) defines the Defects Notification Period at Sub-Clause 1.1.24 as the period stated in the Contract Data – “if not stated, one year” – and specifies that “This period is calculated from the Date of Completion of the Works or Section.” Sub-Clause 11.3 allows extension where a major item of plant cannot be used for its intended purpose, but caps it: “a DNP shall not be extended by more than a period of two years after the expiry of the DNP stated in the Contract Data.” Sub-Clause 11.10 then cuts off plant liability “more than two years after expiry of the DNP for the Plant.”

So the owner’s clock starts at taking over. The vendor’s clock started at shipment. The difference between those two dates is uninsured exposure, and on a long-lead item it can exceed the entire warranty period.

The European supply conditions make the same point from the other direction. Orgalim S 2012, Clause 27: “The Supplier’s liability shall be limited to defects which appear within a period of one year from delivery.” There is no putting-into-operation trigger at all, and Clause 38 imposes an absolute cut-off roughly two years from delivery. Clause 17 confirms that where the purchaser fails to take delivery, the supplier stores the product at the purchaser’s risk and expense – storage does not suspend the Clause 27 clock. The current supply-and-installation edition, Orgalim SI 24 (Brussels, April 2024), runs one year from taking-over at Clause 58, but adds: “If taking-over has been delayed for reasons which are attributable to the Purchaser, the Contractor’s liability for defects shall not … be extended beyond 18 months after delivery of the Product.” That cap is conditional – it bites where the delay is the owner’s. On a capital project, late taking-over is routinely the owner’s: site not ready, utilities absent, feedstock late, permits outstanding.

NEC4 behaves differently and is worth knowing: it sets no numeric default. Both the defects date and the defect correction period are blank Contract Data entries; the commonly used figures are 52 weeks after Completion and four weeks respectively. The long-tail protection lives in secondary Option X18, which is optional.

Back-to-back is a drafting aspiration, not a result

The usual comfort is that the EPC contractor will pass claims through to the equipment vendor. Two reported judgments show how that works in practice.

In Energy Works (Hull) Limited v MW High Tech Projects UK Limited [2022] EWHC 3275 (TCC), Pepperall J awarded the owner £117,195,361.27 on termination plus £2,152,021.55 on major defect claims against the EPC contractor. The contractor’s third-party claim against the equipment supplier, Outotec, largely failed: contribution claims on four of five defects were dismissed because notification under IChemE Yellow Book clause 37.2 was a condition precedent that had not been satisfied, and clause 45.2’s exclusive remedies provision barred any freestanding warranty claim outside that machinery. Outotec’s counterclaim succeeded in US$6,858,466.71. The chain broke on notification timing, not on the merits of the defects.

In Maersk Oil UK Ltd v Dresser-Rand (UK) Ltd [2007] EWHC 752 (TCC), a gas compression package for the Janice A floating production unit carried a 24-month warranty – but Clause 33.1 provided that the Inspection Release Note issued on satisfactory factory inspection “shall be the commencement of the warranty period.” Delivery followed eight months after award; the judgment records that “commissioning did not occur until April of 1999.” A claim of £7,927,487 recovered £1,930,683.11, liability in any event capped at the purchase price of the unit concerned on a package originally priced at £3,133,400.

The assignment mechanism is weaker than it reads, too. In a real executed EPC contract filed with the SEC (Quaker Chemical / FMC Technologies, Middletown Plant Expansion, 14 May 2008), Clause 16.7 requires the contractor to “use its best efforts to obtain for the benefit of the Owner, the best warranties and guarantees that it is possible to secure from its Subcontractors without impact to cost.” An obligation of effort, qualified by cost. The contractor is not required to buy a longer warranty – only to pass on whatever it happened to get. Clause 20.1(d)(iii) then makes “assignments of any warranties provided by manufacturers or suppliers of materials” a condition precedent to final completion, which is precisely the moment at which nobody checks whether the assigned warranties have any time left on them.

Storage: the condition everyone accepts and nobody performs

Every one of the supplier terms above conditions the warranty on proper storage. Flowserve: “conditioned upon proper storage, installation, use and maintenance … in accordance with Seller’s written recommendations.” Alfa Laval’s warranty is “null and void” where products are “misused, abused, improperly stored.” Atlas Copco excludes “damage to equipment caused by the failure of the Purchaser to follow Atlas Copco’s written storage and maintenance instructions.” WEG’s motor manual states that failure to follow its instructions “will void the product warranty.”

What those instructions actually demand is substantial. WEG requires the shaft to be rotated manually at least monthly (weekly for oil-mist bearings), relative humidity not exceeding 60%, space heaters energized, insulation resistance measured periodically, bearings relubricated after six months and replaced after two years of storage. DESMI’s pump storage manual (T1534 Rev. C) requires preserving fluid reapplied every three months, shafts turned every four weeks for drained pumps, and bearing grease replaced if storage exceeds six years. Aerovent’s long-term storage procedure (ES-323, February 2023) requires monthly rotation with the shaft repositioned 180 degrees and states that “Storage records should be maintained that indicate the above requirements have been followed.” Virginia Transformer’s manual goes furthest: nitrogen pressure maintained at 1–2 psi at all times, readings recorded regularly, and – verbatim – “Megger reading per section 5.5 and date of energization must be recorded and sent to the supplier within 15 days of energization for the warranty to be valid.” A documentation duty falling due at exactly the moment a commissioning team is least likely to be doing paperwork.

That these regimes are not performed is not speculation. Engineers from HPCL-Mittal Energy’s Guru Gobind Singh Refinery, reporting on commissioning across more than 5,000 rotating machines at the 2014 Turbomachinery and Pump Symposia, described high vibration in twelve FD/ID fans at start-up traced to water separating out of bearing grease and rusting the bearings – the corrective finding being that the grease should have been replaced with preservation oil on receipt at site. They also found dry gas seals with the vacuum wrap “totally damaged” and the seals soiled. The paper estimates production loss at a 9 MMTPA refinery at about US$1.7 million per day. It never once mentions warranty. The people closest to the problem treat preservation failure as a reliability and schedule issue; its commercial dimension is invisible to them.

No reported judgment was found deciding squarely that a storage failure voided a capital project warranty. The contractual hooks are everywhere; the litigated precedent is not. The practical exposure is evidential: the owner carries the burden of showing the regime was followed, and without a log cannot discharge it.

The handover standard has no field for any of this

CFIHOS, the industry’s capital facilities information handover specification published by IOGP as JIP36, defines the data an owner receives at completion. Its version 2.0 core reference data library contains an equipment warranty end date attribute – “The date at which the warrant on the equipment will end” – classified as Optional. A machine search of the entire data dictionary returns exactly two occurrences of “warrant,” that attribute and one unrelated use. There is no warranty start date, no attribute for the event that starts it, and no reference to the contract term that defines it. The end date the standard asks for is therefore unauditable.

Worse, the date that six of the nine supplier clauses above actually turn on does not exist either. The complete set of date attributes on the equipment entity is actual purchase date, actual installation date, actual start-up date and warranty end date – all Optional. There is no equipment delivery date and no receipt date anywhere in CFIHOS v2.0. The only delivery dates in the dictionary sit on the purchase-order item entity, and both are forecasts rather than actuals. The entire equipment entity runs to seventeen attributes, of which exactly two are not optional: the equipment code and the class name. Serial number, manufacturer, purchase order number, start-up date and warranty end date are all optional – and the standard’s own note on serial number concedes that “During the project this field may not be provided as the equipment is not received.”

Preservation fares no better. Searching the library for “preserv” and “storage” returns no preservation or storage attribute on equipment or any equipment class property. Preservation appears only as a document type – CFIHOS-70000154, “handling, shipping, storage procedure,” defined to include “detail preservation procedure detailing inspection periods, materials required etc.” The plan is a deliverable. The evidence that the plan was executed is not defined at all.

The money is real, and only one end of the chain discloses it

Warranty exposure on this class of equipment is long-dated and material. Siemens Energy’s provisions for warranties stood at €3,792 million at 30 September 2025 (FY2024: €3,721 million), with €2,122 million non-current. GE Vernova’s warranty accrual was US$1,573 million at 31 December 2025, of which 61% was non-current – against Honeywell, whose US$220 million accrual is only 18% non-current. That contrast is the whole argument in two audited numbers: heavy capital equipment carries a structurally long-dated warranty liability, which a twelve-or-eighteen-month clock running from shipment is poorly matched to. Flowserve’s product warranty accrual was US$36.85 million at 31 December 2025; Caterpillar’s US$1,626 million.

The EPC side discloses nothing comparable. Saipem’s 2024 annual report carries no separate warranty provision line. Petrofac’s accounting policy states that it provides “assurance-type warranties which will continue to be accounted for under IAS 37” – folded into general provisions. Fluor, MasTec, Quanta and Baker Hughes carry no warranty tags in their filings. The equipment makers quantify warranty; the contractors do not. The owner sits between them with visibility of neither.

What to fix, and where

None of this is solved by renegotiating terms after award. It is solved by four decisions taken at order placement and one data discipline held through construction.

Specify the trigger. A warranty running from provisional acceptance or first operation, with a stated long-stop measured from the realistic commissioning date rather than shipment, is a commercial term available at tender. It costs something. The point is to price it against the lead time, not discover it at start-up.

Buy the preservation with the equipment. The OEM’s storage regime is a separate document incorporated by reference. Make it a priced scope item with a named performer, a frequency and a log – and make the log a deliverable, since no handover standard will ask for it.

Assign warranties with their dates attached. An assignment that does not identify, per item, the serial number, the actual delivery date, the warranty trigger and the resulting expiry is an assignment of something nobody can value.

Hold the fields. Serial number, purchase order, actual delivery date, storage location, preservation events, commissioning date, warranty trigger and warranty expiry, per tag, maintained from first receipt. CFIHOS will not require them, the EPC contractor will not volunteer them, and reconstructing them from a bill of lading two years later is not a project anyone funds. This is ordinary supplier and purchase-order master data, captured at transaction level – which is exactly the argument for holding the supplier record in a system built to carry it, Dharas among them, rather than in the document management system the engineering contractor hands over.

The equipment on a newly commissioned plant is covered by paper written to protect the party that shipped it. That is not a scandal; it is the market standard, published by Flowserve, Siemens, the World Bank and the EBRD alike. What is avoidable is arriving at first fire without knowing which of your assets are still covered, and being unable to prove it either way.