Local Content Is Decided Before Your First Tender: The Design-Stage Commitments Procurement Inherits

12 min read • 23 October 2026
Local Content Is Decided Before Your First Tender: The Design-Stage Commitments Procurement Inherits

Procurement heads arriving on a newly sanctioned refinery, LNG train or mine are routinely handed a local content percentage and told to deliver it. The reasonable assumption is that the number is a sourcing target – something a well-run tender process, an aggressive supplier development programme and a few quarters of market engagement can move. In most of the jurisdictions where large capital projects are being built in 2026, that assumption is wrong. The number is a legal commitment made at license award or at design stage, approved by a regulator, written into a contract clause, and in several regimes carrying no administrative route to change it.

This matters for a practical reason. If the commitment is a sourcing target, the right response is a better tender. If it is a filed and approved plan tied to engineering decisions already taken, the right response is to find out exactly what was filed, what engineering assumptions it rests on, and what evidence the regulator will ask for – before the first invitation to tender goes out.

The filing precedes the procurement, by statute

Nigeria is explicit. Section 7 of the Nigerian Oil and Gas Industry Content Development Act 2010 reads: “In the bidding for any licence, permit or interest and before carrying out any project in the Nigerian oil and gas industry, an operator shall submit a Nigerian Content Plan (‘the Plan’) to the Board demonstrating compliance with the Nigerian content requirements of this Act.” Two triggers, neither of them a procurement event. Section 8 then makes it a gate: the Board reviews the plan and, if satisfied, “issue[s] a Certificate of Authorization … to the operator for that project.” No certificate, no project.

What goes into that plan is the part procurement teams rarely see. Section 12 requires the plan to set out how the operator and its contractors will give first consideration to Nigerian goods and services, “including specific examples showing how first consideration is considered and assessed by the operator in its evaluation of bids.” The bid evaluation methodology is itself a regulatory filing, approved before bidding opens. NCDMB’s own Guidelines for NCDMB Approvals of Nigerian Oil & Gas Contracting Processes confirms the sequence operationally: Step 1 is the Nigerian Content Plan inclusive of contracting strategy and advert, carrying a Certificate of Authorization with six months’ validity and a ten-day review; Step 5 is the Nigerian Content Compliance Commitment, issued after commercial evaluation and before award. The percentage enters at Step 1 and is merely confirmed at Step 5.

Ghana states the thesis more cleanly than any other instrument reviewed. Regulation 7(1) of L.I. 2204 (gazetted 12 July 2013, in force 20 November 2013): a contractor, subcontractor or licensee shall “before engaging in a petroleum activity prepare and submit a local content plan for approval at the time of submission to the Commission of an application to undertake a petroleum activity.” Regulation 7(2)(a) requires “a long term local content plan which corresponds with the work programme that accompanies the application.” The plan is part of the application file. Regulation 10(3) closes the loop: the Commission takes account of the work programme in the petroleum agreement or licence in determining the minimum levels to be achieved.

Tanzania copied Ghana’s architecture almost word for word – regulation 10 of the Mining (Local Content) Regulations 2018 (GN No. 3 of 2018, signed 9 January 2018) requires the plan “when making application to undertake mining activity,” corresponding to the work programme. GN No. 563 of 2025 (published 12 September 2025, signed 29 August 2025) added a dedicated procurement sub-plan to the mandatory contents of that filing, and a new regulation 13A empowering the Commission to publish, from time to time, a list of goods and services reserved exclusively to 100%-Tanzanian-owned companies – a ring-fence that can expand after a plan has been approved.

Guyana runs on a four-month clock from an event that has nothing to do with procurement. Section 8(1)(b) of the Local Content Act 2021 requires a Local Content Master Plan within four months of the grant of a licence, the transfer of an interest in a licence, or entering a petroleum agreement. Section 9(1)(e) requires it to contain “a statement on, and an estimate of, the value of local content to be acquired, delivered and rendered for Guyana.” Subcontractors inherit the same four-month clock from their own contract date under section 8(2) — which is how an EPC contractor’s procurement team acquires a filed plan it did not write. The Secretariat’s Local Content Annual Plan Submission Guideline (Version 3.0, 22 December 2023) requires next year’s procurement forecast as a mandatory annex. The forward sourcing plan is a ministerial filing.

Brazil: the number attaches to engineering systems, and the exits are closed

Brazil is the strongest evidence available that this is a design problem rather than a sourcing problem. CNPE Resolution No. 11 of 20 December 2023 (published in the Diário Oficial da União, 27 December 2023) sets minimum local content for forthcoming rounds. Article 3(I) states that the commitments “serão definidos em Cláusulas específicas do Contrato e não serão adotados como critério de julgamento das ofertas na Licitação” – defined in specific contract clauses and not used as a criterion for judging bids.

The percentages themselves are the point. For offshore blocks in the production development stage: 30% for well construction, 40% for the collection and offloading system, and 25% for the stationary production unit. Three named engineering systems, three different obligations. Where a FEED engineer draws the boundary between the stationary production unit and the collection and offloading system moves scope between a 25% obligation and a 40% one. No tender can undo that.

Article 3(IV) then removes the escape route for these contracts outright: there will be no application of the exemption mechanism to the minimum percentages. For legacy contracts the relief regime under Resolução ANP nº 726/2018 still exists – exemption on grounds of excessive Brazilian pricing (a threshold that tightened from 25% to 20% to 10% for contracts signed between 1 January 2023 and 31 December 2027) or excessive delivery times. But note what that resolution’s Article 5 says about the second ground: the allegation of excessive delivery time “não será admitida quando restar demonstrado que o Operador induziu à urgência da necessidade de entrega do bem ou serviço, ou teve responsabilidade sobre o atraso no cumprimento do cronograma do projeto.” A waiver on delivery-time grounds is refused where the operator itself created the urgency. Late procurement planning destroys the relief it would otherwise justify. And the window to amend a legacy contract’s local content clause closed on 10 August 2018.

Nigeria’s position is harsher still. The only statutory relief, section 11(4), authorized continued importation where capacity was inadequate – “and such approval by the Minister shall not exceed 3 years from the commencement of this Act.” The Act commenced 22 April 2010. That window shut in April 2013. On the face of the Act, the route to change a Schedule target is an amendment by the National Assembly under section 11(2).

Guyana is the counter-example worth knowing: section 7(3)(b) provides a live, uncapped capacity-gap waiver. But it is a ministerial act, not a procurement decision, and it has to be applied for.

The engineering decisions that cap the ceiling

Nigeria’s Schedule does not set a project-level percentage. It sets targets per project item, in man-hours, tonnage, volume, length, number and litres – FEED and detailed engineering on onshore facilities at 90% of man-hours, on an LNG facility at 50%; pipeline systems and risers at 100% of tonnage; topside process and storage modules at 50%; high-voltage cables at 45% of length against low-voltage at 90%. Section 11(3) binds compliance to the “particular project item, service or product specification set out in the schedule.” A package boundary that puts scope under one heading rather than another changes the legal obligation. Section 53 removes one decision from the table entirely: “all operators, project promoters, contractors and any other entity engaged in the Nigerian oil and gas industry shall carry out all fabrication and welding activities in the country.”

Indonesia is the only regime that names the design stage in terms. SKK Migas’s PTK-007 Revision 05 (4 April 2023) requires SKK Migas to set the TKDN achievement target in every Plan of Development – the pre-FID approval instrument – and obliges contractors to use domestic products at the planning stage, “termasuk tahap Front End Engineering Design (FEED)”, in determining goods specifications. Use of foreign specifications requires prior consultation with SKK Migas or the Ministry of Energy and Mineral Resources. The specification written at FEED is the thing that decides whether local content is achievable, and Indonesia regulates it at that moment.

The downside risk of getting the design decision wrong is not a lower percentage – it can be zero. Under Permenperin 35/2025, Pasal 9(2) excludes from TKDN calculation altogether goods whose raw materials and components are entirely imported, goods produced only from packing or packaging, and goods from painting, coloring, cutting, slicing or dilution that does not change the HS code. Pasal 6 scores direct labor at 0% where Indonesian nationals are under 50% of direct labor; Pasal 7 scores factory overhead at 0% where the business actor has not invested in Indonesia. A strategy of “import the package and assemble locally” does not produce a reduced number. It produces nothing.

Kazakhstan’s unified methodology (Order No. 260 of 20 April 2018, as replaced in a new edition by Order No. 240 of 29 April 2022) applies the same binary logic to contracts. Absent a CT-KZ certificate of origin, the goods share Мᵢ = 0. For subsoil-use contracts concluded from 1 January 2015, each contract in the chain carries a coefficient Kj equal to 1 if a Kazakhstani producer of works and services performs it, and 0 otherwise. Who holds each subcontract – a work-breakdown decision – determines the number outright.

Why procurement arrives after the decision

The timing is structural, not a failure of diligence. AACE International Recommended Practice 18R-97 classifies the estimate a project is sanctioned on as a Class 3, prepared at 10% to 40% of complete project definition, with an accuracy range of roughly −10/−20% to +10/+30%. The project is funded, the budget fixed and the regulatory commitment filed when engineering is between a tenth and two-fifths done – but that fraction already contains the equipment list, the package boundaries and the procurement plan.

The Construction Industry Institute’s Project Definition Rating Index validation found industrial projects scoring above 200 (poorer front-end definition) ran +18.0% over budget against −5.1% under for better-defined ones – a 23.1-point swing – and 14.0% against 0.8% on schedule. Tellingly, the PDRI scores “identify long lead/critical equipment and materials,” “procurement procedures and plans” and “procurement responsibility matrix” as front-end planning elements. The industry’s own definition instrument grades procurement readiness before procurement is staffed.

A caution worth stating: the familiar claim that 80% of cost is determined in the first 20% of design cannot be traced to any dated, named publication, and a peer-reviewed paper exists specifically attacking its weaker cousin (Barton, Love and Taylor, “Design determines 70% of cost? A review of implications for design evaluation,” Journal of Engineering Design, 12(1), 2001). The AACE and CII figures say the same thing with document numbers.

The capacity nobody counted

The cost of getting this wrong is visible in Nigeria. NCDMB’s own survey of fabrication yards recorded total fabrication tonnage achieved of 228,260 tonnes in 2017, up from under 50,000 tonnes per annum in 2010, and in April 2025 the Board stated that the country now has excess fabrication capacity. Yet reporting from February 2025 recorded that Samsung Heavy Industries Nigeria, which trained 560 welders for the Egina project and peaked above 1,000 workers, had a workforce of 131; and that Africoat Nigeria’s US$42 million coating plant had stood idle since its completion in 2017. The yards exist. Their order books are decided by package strategy settled during front-end engineering, not by their own capability.

What a procurement function can actually control

Three things, all of them data.

First, obtain what was filed. The Nigerian Content Plan, the Ghanaian or Tanzanian long-term plan, the Guyanese Master Plan and its procurement sub-plan, the Brazilian contract clause, the Indonesian POD target. These are approved documents with specific numbers, specific measured units and specific commitments about fabrication location and contracting strategy. A procurement team that has not read them is working from a summary.

Second, record the measured unit, not just the percentage. A 50% target in tonnage, a 90% target in man-hours and a 60% target in number of valves require three different datasets, captured at order, from the supplier, in the format the regulator audits. None of it can be reconstructed afterwards from a general ledger. This is the point at which local content stops being a reporting exercise and becomes a supplier-data architecture: the attributes that prove compliance – origin, certificate number and expiry, measured quantity, the certified percentage under the applicable formula – have to exist as fields on the supplier and purchase-order record from the first award. Platforms built for supplier relationship management and local content reporting in capital projects, Dharas among them, exist because that capture has to happen at transaction level and in real time, not in a spreadsheet at year end.

Third, build the capability baseline while the design is still moving. The evidence that supports a waiver, a capacity-gap case or a specification change is a documented market survey – which is exactly what Indonesia’s PTK-007 demands when a contractor claims domestic capacity is insufficient. If that file is assembled during FEED, it is an input to the design. Assembled after award, it is an excuse the regulator has already told you it will not accept.

The local content percentage is not the first decision in the chain. It is the consequence of decisions about package boundaries, fabrication location, specification standards and contracting strategy – decisions taken by engineers, approved by a regulator, and signed before the procurement organisation was formed. The function that reads the filing early stops inheriting a number and starts shaping one.